Sewage Lift Station #5 Piping Rehabilitation and Replacement

Yellowknife, Northwest Territories

completeWastewaterCWWF
Federal contribution
$1.3M
$1,312,000
Federal share75%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Yellowknife
Construction start
Nov 1, 2017(actual)
Construction end
Sep 6, 2019(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2019

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47619 in the federal list. How to read these figures.