Supervisory Controls and Data Acquisition System Upgrades for pumphouses and lift stations.
Yellowknife, Northwest Territories
Federal contribution
$671,420
Federal share56%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Yellowknife
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Mar 13, 2020(actual)
Against the original forecast
- Construction start5 months earlyforecast Nov 1, 2017
- Construction end3 weeks earlyforecast Mar 31, 2020
Also in Yellowknife
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47626 in the federal list. How to read these figures.