Northern Piped Water and Sewer Research

Yellowknife, Northwest Territories

completeDrinking WaterCWWF
Federal contribution
$60,000
Federal share75%

of $80.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 6, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Mar 31, 2019(actual)
Construction end
Mar 13, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 1, 2018
  • Construction end3 weeks earlyforecast Mar 31, 2020

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47630 in the federal list. How to read these figures.