Wastewater Collection and Storm System Upgrades
Federal contribution
$3.7M
$3,700,000
Federal share50%
of $7.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Regina
- Construction start
- Jul 5, 2017(actual)
- Construction end
- Sep 5, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end2 months lateforecast Jun 28, 2019