Caswell Hill Water Main and Service Connection Replacements
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Apr 17, 2017(actual)
- Construction end
- Nov 15, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 1, 2017
- Construction end4 months earlyforecast Mar 31, 2019
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47658 in the federal list. How to read these figures.