Back to projects

Service Connection Line Replacements

Saskatoon, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$2.1M
$2,075,000
Federal share50%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saskatoon
Construction start
Jul 14, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2019

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47662 in the federal list. How to read these figures.