Water Main Lining
Federal contribution
$3.5M
$3,525,000
Federal share50%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Dec 16, 2017(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2017
- Construction end2 weeks lateforecast Nov 30, 2017
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47663 in the federal list. How to read these figures.