Electoral Area D - Area D Integrated Water System Upgrade
Fraser Valley, British Columbia
Federal contribution
$106,250
Federal share50%
of $212.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Fraser Valley
- Construction start
- Aug 8, 2017(actual)
- Construction end
- Mar 29, 2018(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Oct 1, 2017
- Construction end8 weeks lateforecast Jan 31, 2018
Also in Fraser Valley
- Fraser Valley - Cultus Lake North Wastewater Treatment Plant$5.5M
- Fraser Valley - Station House, Community Rest Stop and Museum: Boston Bar/North Bend, British Columbia$1.1M
- Fraser Valley - Hope and Area Recreation Centre Geothermal Heat Recovery$1.1M
- Electoral Area E - Baker Trails Estate Wastewater Treatment System Replacement$823.2K
- Boston Bar and Surrounding Area Fibre to the Home$254.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47677 in the federal list. How to read these figures.