Back to projects

Electoral Area B - Dogwood Valley Water System Upgrade

Fraser Valley, British Columbia

completeDrinking WaterCWWF
Federal contribution
$99,762
Federal share50%

of $199.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 27, 2017(actual)
Construction end
Mar 14, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 31, 2017
  • Construction end8 weeks lateforecast Jan 19, 2018