Back to projects

Greater Nanaimo Pollution Control Centre: Centrifuge and Polymer System

Nanaimo, British Columbia

completeWastewaterCWWF
Federal contribution
$654,500
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
May 23, 2017(actual)
Construction end
Mar 25, 2020(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jul 5, 2017

Also in Nanaimo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47692 in the federal list. How to read these figures.