Back to projects

Greater Saint John Field House

Saint John, New Brunswick

completeRecreationNRP
Federal contribution
$6.0M
$6,000,000
Federal share24%

of $25.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 5, 2017
201820192020
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Feb 13, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 1, 2017
  • Construction end14 months lateforecast Oct 31, 2018

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47730 in the federal list. How to read these figures.