Greater Saint John Field House
Federal contribution
$6.0M
$6,000,000
Federal share24%
of $25.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2017
201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Greater Saint John Field House Foundation Inc.
- Construction start
- Feb 13, 2018(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 1, 2017
- Construction end14 months lateforecast Oct 31, 2018
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47730 in the federal list. How to read these figures.