Schedule
Announced and approvedMay 25, 2017
20172018201920202021
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Bonaventure
- Construction start
- Apr 1, 2020(actual)
- Construction end
- Mar 8, 2021(actual)
Against the original forecast
- Construction start13 months lateforecast Mar 1, 2019
- Construction end14 months lateforecast Dec 31, 2019