Water reservoir on Louisbourg Avenue

Bonaventure, Quebec

completeDrinking WaterCWWF
Federal contribution
$2.9M
$2,921,825
Federal share50%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2017
20182019
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Bonaventure
Construction start
Jul 1, 2017(actual)
Construction end
Dec 21, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 22, 2017