Water pipe replacement
Federal contribution
$590,136
Federal share46%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2017
Built
Approved 2 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Bonaventure
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Dec 17, 2017(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 29, 2017
- Construction end15 months earlyforecast Mar 31, 2019
Also in Bonaventure
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49157 in the federal list. How to read these figures.