Schedule

Announced and approvedApr 28, 2017
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Bonaventure
Construction start
Jul 1, 2017(actual)
Construction end
Dec 17, 2017(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 29, 2017
  • Construction end15 months earlyforecast Mar 31, 2019