Installation of required concrete works at five (5) transit shelter locations to address accessibility constraints

Chatham-Kent, Ontario

completePublic TransitPTIF
Federal contribution
$29,874
Federal share21%

of $140.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019202020212022
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 16, 2021(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start4.3 years lateforecast May 5, 2017

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47780 in the federal list. How to read these figures.