completePublic TransitPTIF
Federal contribution
$43,351
Federal share43%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2019(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 10, 2017
  • Construction end3 months lateforecast Dec 31, 2019

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47782 in the federal list. How to read these figures.