Installation of required concrete works at fifty (50) transit stop locations to improve customer service and security

Chatham-Kent, Ontario

completePublic TransitPTIF
Federal contribution
$19,086
Federal share19%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019202020212022
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Sep 15, 2020(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start3.4 years lateforecast May 5, 2017
  • Construction end4 months lateforecast Sep 15, 2021

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47787 in the federal list. How to read these figures.