Installation of twenty-seven (27) new solar packages by Mountain Shelter Solutions at existing transit passenger shelter locations

Chatham-Kent, Ontario

completePublic TransitPTIF
Federal contribution
$75,712
Federal share47%

of $160.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Dec 1, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Nov 20, 2017
  • Construction end3 months lateforecast Dec 31, 2019