Replace Existing four (4) Parabuses
Federal contribution
$174,010
Federal share46%
of $380.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
2017
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Sault Ste. Marie
- Construction start
- May 31, 2017(actual)
- Construction end
- Nov 24, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 2, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Sault Ste. Marie