Restoration of Four (4) Sault Transit Pedestrian Shelters

Sault Ste. Marie, Ontario

completePublic TransitPTIF
Federal contribution
$8,932
Federal share45%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Sault Ste. Marie
Construction start
May 31, 2017(actual)
Construction end
Oct 25, 2017(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 2, 2017
  • Construction end5 months earlyforecast Mar 31, 2018