Northern Transfer Location
Federal contribution
$75,000
Federal share50%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Fort Saskatchewan
- Construction start
- Jul 1, 2016(actual)
- Construction end
- Mar 15, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jul 15, 2016
- Construction end2 weeks earlyforecast Mar 31, 2018
Also in Fort Saskatchewan
- Highway 15/21 Corridor Improvements - 94th Street to 101 Street$3.0M
- Alberta Capital Region Wastewater Commission (ACRWC) - Waste Gas Burner Facility Upgrade$1.8M
- Fort Saskatchewan Council Chamber Upgrades$120.3K
- Fort Saskatchewan Smart Fare and Smart Bus$79.8K
- Fort Saskatchewan - City Hall Front Counter Renovations (Main Floor)$41.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47819 in the federal list. How to read these figures.