Alberta Capital Region Wastewater Commission (ACRWC) - Waste Gas Burner Facility Upgrade
Federal contribution
$1.8M
$1,780,000
Federal share40%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2020
202020212022
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Alberta Capital Region Wastewater Commission
- Construction start
- May 20, 2020(actual)
- Construction end
- Oct 31, 2022(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Nov 30, 2022
Also in Fort Saskatchewan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54401 in the federal list. How to read these figures.