Fort Saskatchewan Council Chamber Upgrades

Fort Saskatchewan, Alberta

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$120,333
Federal share26%

of $458.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Fort Saskatchewan
Construction start
Aug 1, 2021(actual)
Construction end
Mar 1, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 31, 2021
  • Construction end3 months lateforecast Dec 1, 2021