Bus Pull-outs and Bus stops

Leduc, Alberta

completePublic TransitPTIF
Federal contribution
$42,500
Federal share50%

of $85.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
201720182019
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Leduc
Construction start
Jul 17, 2017(actual)
Construction end
Sep 1, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2017
  • Construction end17 months lateforecast Mar 31, 2018

Also in Leduc

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47821 in the federal list. How to read these figures.