Bus Pull-outs and Bus stops
Federal contribution
$42,500
Federal share50%
of $85.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
201720182019
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Leduc
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Sep 1, 2019(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 1, 2017
- Construction end17 months lateforecast Mar 31, 2018
Also in Leduc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47821 in the federal list. How to read these figures.