Purchase of two accessible buses (Care A Vans)
Federal contribution
$115,000
Federal share50%
of $230.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Sarnia.
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Apr 1, 2018(actual)
Against the original forecast
- Construction end9 months earlyforecast Dec 31, 2018