Replace 2 existing Paravan vehicles

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$80,000
Federal share50%

of $160.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 29, 2017(actual)
Construction end
Apr 17, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2017
  • Construction end2 weeks lateforecast Mar 31, 2018

Also in St. Catharines