Repair bay addition at maintenance facility

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$980,383
Federal share45%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 1, 2017(actual)
Construction end
Jun 28, 2018(actual)

Against the original forecast

  • Construction start5 months earlyforecast Oct 30, 2017
  • Construction end2 months earlyforecast Aug 31, 2018

Also in St. Catharines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47890 in the federal list. How to read these figures.