Install automatic passenger counting on all 70 of our conventional vehicles

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$360,000
Federal share50%

of $720.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 31, 2017(actual)
Construction end
Nov 17, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 1, 2017
  • Construction end3 months lateforecast Aug 31, 2017

Also in St. Catharines