Back to projects

Remove four underground tanks for transmission fluid, waste oil, paint and engine oil, and replace with three aboveground tanks

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$87,411
Federal share44%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 25, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017