Back to projects

Upgrade video camera system at maintenance facility and bus terminal

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$54,229
Federal share49%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 11, 2017(actual)
Construction end
Oct 12, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2017
  • Construction end3 weeks earlyforecast Oct 31, 2017

Also in St. Catharines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47895 in the federal list. How to read these figures.