Back to projects

Purchase and install new emergency generator for maintenance facility and garage

St. Catharines, Ontario

completePublic TransitPTIF
Federal contribution
$172,506
Federal share49%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Oct 1, 2017(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 1, 2017
  • Construction end4 weeks earlyforecast Mar 31, 2019