Purchase and install new emergency generator for maintenance facility and garage
Federal contribution
$172,506
Federal share49%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
201720182019
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of St. Catharines
- Construction start
- Oct 1, 2017(actual)
- Construction end
- Feb 28, 2019(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 1, 2017
- Construction end4 weeks earlyforecast Mar 31, 2019
Also in St. Catharines
- St. Catharines Arts Centre$18.0M
- Carlisle Street Garage Replacement$9.3M
- HVAC; Handwashing and Washrooms; Online Learning Support; New Portable; Building Ventilation Controls; Creating New Classroom Space$7.8M
- Facility Expansion$3.9M
- Purchase three 60' buses and nine 40' buses to replace existing vehicles for conventional service$3.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47899 in the federal list. How to read these figures.