Purchase one new service truck
Federal contribution
$25,657
Federal share34%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
2017
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Timmins
- Construction start
- Feb 1, 2017(actual)
- Construction end
- Sep 7, 2017(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Nov 1, 2017
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47914 in the federal list. How to read these figures.