Install nineteen (19) Passenger Counters to conventional buses.
Federal contribution
$40,000
Federal share50%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Timmins
- Construction start
- Feb 1, 2017(actual)
- Construction end
- Mar 30, 2018(actual)
Against the original forecast
- Construction end4 weeks lateforecast Feb 28, 2018
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47917 in the federal list. How to read these figures.