Install 100 new retro-reflective Bus Stop Signs
Federal contribution
$2,290
Federal share23%
of $10.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Timmins
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Oct 15, 2018(actual)
Against the original forecast
- Construction end8 months lateforecast Jan 31, 2018