Replace Windows and Doors at Transit Terminal
Federal contribution
$44,833
Federal share45%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Timmins
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Apr 10, 2018(actual)
Against the original forecast
- Construction end6 weeks lateforecast Feb 28, 2018