Back to projects

SMART Transit - Replace existing vehicles

Hanover, Ontario

completePublic TransitPTIF
Federal contribution
$84,385
Federal share50%

of $168.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 16, 2017
ApprovedMar 19, 2018
20172018
Built

Approved 14 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Hanover
Construction start
Apr 1, 2017(actual)
Construction end
Dec 21, 2017(actual)