Fleet Replacement (Two Units)
Federal contribution
$99,696
Federal share47%
of $210.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
201720182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Wasaga Beach
- Construction start
- Mar 1, 2017(actual)
- Construction end
- Sep 1, 2019(actual)
Against the original forecast
- Construction start10 months earlyforecast Jan 1, 2018
- Construction end17 months lateforecast Mar 31, 2018