Pouch Cove Drinking Water
Pouch Cove, Newfoundland and Labrador
Federal contribution
$1.4M
$1,427,413
Federal share33%
of $4.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2017
20182019202020212022
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Pouch Cove
- Construction start
- Feb 16, 2018(actual)
- Construction end
- Dec 30, 2021(forecast)
Against the original forecast
- Construction start4 months earlyforecast Jun 16, 2018
Also in Pouch Cove