Bragg's Lane - Substandard Water Main

Pouch Cove, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$83,443
Federal share40%

of $208.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Pouch Cove
Construction start
May 1, 2023(actual)
Construction end
Jul 31, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 15, 2023
  • Construction end4 months earlyforecast Dec 8, 2023