Water, Sewer and Retaining Wall Upgrades – Noseworthy’s Lane

Pouch Cove, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$148,247
Federal share40%

of $370.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Pouch Cove
Construction start
Oct 1, 2020(actual)
Construction end
Dec 4, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 15, 2020
  • Construction end6 months earlyforecast Jun 15, 2021