Rehabilitation of the Backwash Filter Room at the Dunnville Water Treatment Plant

Haldimand, Ontario

completeDrinking WaterCWWF
Federal contribution
$275,000
Federal share50%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018201920202021
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Haldimand
Construction start
Oct 1, 2017(actual)
Construction end
Dec 31, 2020(actual)

Against the original forecast

  • Construction start17 months lateforecast May 1, 2016
  • Construction end9 months earlyforecast Sep 30, 2021

Also in Haldimand

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48049 in the federal list. How to read these figures.