Rehabilitation (concrete repair and sealing) of the West Reservoir at the Nanticoke Water Treatment Plant

Haldimand, Ontario

completeDrinking WaterCWWF
Federal contribution
$43,796
Federal share40%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Haldimand
Construction start
Nov 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 31, 2017
  • Construction end2 months lateforecast Oct 31, 2017