Rehabilitation (concrete repair and sealing) of the West Reservoir at the Nanticoke Water Treatment Plant
Federal contribution
$43,796
Federal share40%
of $110.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Haldimand
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 31, 2017
- Construction end2 months lateforecast Oct 31, 2017
Also in Haldimand
- Grandview Lodge Long Term Care Home -HVAC, Controls, Electrical Infrastructure and Generator Upgrades$3.0M
- Grandview Lodge Long Term Care HVAC Replacement$2.6M
- Replacement of Ouse Street North, Kerr Street, Norton Street and Mohawk Street Watermains$673.2K
- Rehabilitation (surface repairs and recoating) of the Cayuga Standpipe$460.0K
- Replacement of Cast Iron Watermain in Hagersville$350.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48050 in the federal list. How to read these figures.