Installation of Baffling Systems (curtains) in the East and West Reservoirs at the Nanticoke Water Treatment Plant

Haldimand, Ontario

completeDrinking WaterCWWF
Federal contribution
$175,000
Federal share50%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Haldimand
Construction start
Oct 1, 2017(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 31, 2017
  • Construction end5 months earlyforecast Mar 31, 2021