Design, Planning and Site Preparation of New Maintenance & Storage Facility in lower Hamilton
Federal contribution
$6.0M
$5,994,941
Federal share35%
of $17.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018201920202021
Built
Approved 12 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Aug 24, 2017(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2017
- Construction end16 months lateforecast Mar 31, 2020
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48124 in the federal list. How to read these figures.