Design, Planning and Site Preparation of New Maintenance & Storage Facility in lower Hamilton

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$6.0M
$5,994,941
Federal share35%

of $17.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018201920202021
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Aug 24, 2017(actual)
Construction end
Jul 31, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2017
  • Construction end16 months lateforecast Mar 31, 2020