Fleet Expansion as per Ten Year Local Transit Strategy, 2017 (5) and 2018 (11)

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$4.9M
$4,869,121
Federal share47%

of $10.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Apr 28, 2017(actual)
Construction end
Aug 31, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end2 months lateforecast Jun 30, 2019

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48125 in the federal list. How to read these figures.