Transit shelter and bus stop rehabilitation and development of technical guideline
Federal contribution
$2.9M
$2,880,179
Federal share41%
of $7.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018201920202021
Built
Approved 12 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2017
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48126 in the federal list. How to read these figures.