226 Automated Passenger Counters

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$1.1M
$1,100,000
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
May 19, 2017(actual)
Construction end
Apr 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2017
  • Construction end11 months earlyforecast Mar 31, 2019