226 Automated Passenger Counters
Federal contribution
$1.1M
$1,100,000
Federal share50%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built
Approved 12 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- May 19, 2017(actual)
- Construction end
- Apr 30, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 1, 2017
- Construction end11 months earlyforecast Mar 31, 2019
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48127 in the federal list. How to read these figures.