Transit Network Review and Installation of Transit Priority Measures

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$337,999
Federal share42%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
201820192020202120222023
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Oct 23, 2017(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start10 months lateforecast Jan 1, 2017