Transit Network Review and Installation of Transit Priority Measures
Federal contribution
$337,999
Federal share42%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedMar 19, 2018
201820192020202120222023
Built
Approved 12 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction start10 months lateforecast Jan 1, 2017
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48128 in the federal list. How to read these figures.