Vehicle hoist replacements (22) and 3 new hoists at Mountain Transit Centre

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$2.8M
$2,750,536
Federal share39%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018201920202021
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
May 29, 2017(actual)
Construction end
Jul 31, 2021(actual)

Also in Hamilton