Sustainable transportation/transit connections - sidewalks
Federal contribution
$1.2M
$1,187,980
Federal share39%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Apr 28, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 1, 2017
- Construction end7 months earlyforecast Mar 31, 2019
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48131 in the federal list. How to read these figures.